How Architects Can Reduce RFIs, Change Orders & Overruns

Technology systems like IT, AV, security, DAS, and access control are some of the most complex and coordination-intensive elements of any modern building project. They’re also the source of more than their fair share of RFIs, change orders, and budget surprises. Not because the technology is unpredictable, but because architects often treat them as obstacles to be resolved later.

TL;DR

  • Most RFIs, change orders, and budget overruns on technology-intensive projects trace back to technology scope that was deferred or left vague during design.
    - Common causes include vague technology narratives in construction documents, uncoordinated routing between technology and MEP disciplines, and bid documents that do not support accurate pricing.
  • The most reliable fixes are engaging a technology consultant at schematic design, completing MEP coordination before construction documents are issued, and writing clear, unambiguous specifications.
  • Accurate technology cost estimating and continuity through construction administration keep budgets defensible and keep change orders tied to real owner decisions rather than avoidable documentation gaps.
  • A vendor-neutral technology consultant covering Divisions 25, 27, and 28 helps architects prevent these problems before they become cost events.

Global construction inefficiencies cost an estimated $1.6 trillion annually, with overruns ranging from 20% to 45%.1 Overruns, along with too many change orders and RFIs, can erode owner trust. The good news is that the majority of these problems are preventable – and they almost always trace back to decisions made (or deferred) well before the first shovel hits the ground.

In this blog, we break down the most common causes of construction RFIs, change orders, and budget overruns on technology-intensive projects, then walk through the strategies and practices that prevent them.

Why Do RFIs and Change Orders Happen on Technology-Heavy Projects?

RFIs and change orders rarely appear out of nowhere. On technology-intensive projects, they’re almost always the downstream consequence of something that wasn’t resolved in the design phase.

Understanding the root causes can make them far easier to prevent. Here’s what to watch out for:

Vague Technology Narratives in Construction Documents

When technology specifications for architects default to performance language – “provide a system capable of” or “coordinate with owner’s IT” – contractors are left to make assumptions and price accordingly.

Do your technology specs leave room for contractor assumptions? TMC can help you clear them up.

Every contractor will interpret differently. While some will under-scope to stay competitive, others will pad for uncertainty. Neither produces an accurate bid, and the gaps almost always surface as RFIs or change orders during construction.

Detailed, coordinated technology specifications at the CD stage give contractors the information they need to build. The more precise the specification, the less room there is for ambiguity to become a cost event.

Uncoordinated Routing Between Technology and MEP Disciplines

Technology systems share physical space with mechanical, electrical, and plumbing work in ways that aren’t always obvious until someone is in the ceiling trying to run conduit. Above-ceiling pathways, equipment room sizing, power and cooling loads, and conduit routing all need to be resolved in the design phase – not discovered by a contractor in the field.

If you don’t complete technology and MEP coordination before CDs are issued, contractors will likely encounter conflicts during installation. Those conflicts generate RFIs, which generate delays, which then generate change orders. The downstream cost of a coordination gap that could have been caught in design is almost always a multiple of what it would have taken to resolve it upstream.

Bid Documents That Don’t Support Accurate Pricing

A bid document’s job is to give contractors everything they need to price the scope accurately. Contractors fill in the gaps with assumptions if the technology scope is too high-level, resulting in a bid spread that tells you very little about actual cost, and a contract that almost guarantees change orders when the details eventually get resolved.

Detailed bid documents compress scope ambiguity at the front end, which means fewer surprises at the back end. This is one of the clearest ways that investment in thorough upfront documentation pays for itself in project outcomes.

Global construction inefficiencies cost an estimated $1.6 trillion annually.

How To Manage Scope in AV IT Infrastructure Architectural Projects

AV and IT infrastructure present coordination challenges that aren’t always intuitive for project teams whose primary expertise is in the built environment rather than technology systems. These disciplines involve dense interdependencies – between systems, between trades, and between the technology environment and the owner’s operational requirements.

A few of the most common complexity drivers on AV IT infrastructure architectural projects include:

  • System Integration Requirements: AV systems, IT networks, access control, and building automation systems increasingly need to communicate with each other. Integration requirements that aren’t specified upfront become scope disputes or costly add-ons during commissioning.
  • Owner IT Standards: Many owners have existing technology environments with specific standards for networking equipment, software platforms, and vendor relationships. Systems designed without accounting for these standards often require changes before they can be accepted, generating change orders late in the project.
  • Phasing and Operational Continuity: Projects that involve occupied buildings or phased construction require technology systems to be designed with operational continuity in mind. A scope that doesn’t account for phasing constraints creates field problems that are expensive to solve under time pressure.

TMC’s technology design services for architectural projects address this complexity through early engagement and thorough documentation – ensuring that the systems specified are the systems the owner needs, and that the documents support a clean construction process.

How To Avoid Technology Change Orders in Architecture

The question during any project isn’t whether there will be change orders, but whether they’ll reflect genuine owner-driven scope changes or avoidable gaps in your original documents.

Change orders happen on every project. Make sure they don’t reflect avoidable gaps in your documents.

On technology-heavy projects, avoidable change orders tend to cluster around a few predictable scenarios:

  • The technology scope wasn’t fully defined in the bid documents, requiring additional work orders to complete systems that were assumed to be included.
  • Owner scope changes – a reconfigured space, an added function, a change in AV system requirements – are evaluated in isolation rather than against the existing technology infrastructure plan, leading to cascading impacts that are priced reactively rather than proactively.
  • Coordination conflicts between technology and other trades are discovered in the field, requiring redesign, rerouting, or additional materials and labor that weren’t in the original contract.
  • Substitution requests for technology equipment are evaluated without sufficient technical review, leading to compatibility issues that require correction after installation.

Engaging a technology consultant like TMC through construction administration can provide the continuity you need to manage these scenarios before they become cost events. When an owner wants to change something, we can evaluate that change against the existing design and infrastructure plans quickly – because we know the project. That speed matters when a contractor is waiting for direction.

How Architects Can Reduce Construction RFIs

Projects with well-coordinated, detailed construction documents generate fewer RFIs because contractors have the information they need. Projects with gaps, ambiguities, and unresolved coordination issues generate RFIs at every turn.

The strategies that most reliably reduce construction RFIs on technology-intensive projects are consistent:

Engage Technology Consultants at Schematic Design

Changes at the schematic design stage cost a fraction of what they cost at CDs or during construction. A technology consultant brought in at SD can translate owner requirements into infrastructure narratives, identify space and pathway needs, and flag coordination issues before they’re locked into the design.

Issues caught during MEP coordination are resolved through redlines – not RFIs, change orders, and field delays.

Resolve MEP Coordination Before CDs Are Issued

The single highest-leverage action for reducing field RFIs on technology projects is completing MEP coordination before construction documents are issued. Conduit conflicts, equipment room sizing issues, and power and cooling gaps that are caught in coordination are resolved through redlines – not through RFIs, change orders, and field delays.

Use Construction Coordination Technology Systems Effectively

Systems like BIM coordination platforms and construction management tools can identify conflicts like conduit routing clashes, equipment room sizing issues, and power and cooling constraints before they surface as field problems.

However, the software is only as effective as the expertise guiding its use. A technology consultant working with these tools provides the discipline-specific knowledge and problem-solving judgment that automated detection can’t deliver.

Write Clear, Unambiguous Specifications

Every ambiguity in a technology specification is a potential RFI. Make sure your specs:

  • Define the scope clearly
  • Establish performance requirements explicitly
  • Address contractor interfaces

Clear specifications give contractors a complete picture of what’s required, which means fewer questions and more accurate execution.

Stay Engaged Through Construction Administration

RFIs that do come in during construction should be reviewed by the same team that produced the documents. A consultant who responds to RFIs without the context of the original design intent, or who responds inconsistently because institutional knowledge has been lost, will generate more questions. Continuity through CA is what keeps the project moving.

Only a quarter of construction projects come within 10% of their original budget.

Why Is Accuracy Essential for Building Technology Cost Estimating?

Budget accuracy is one of the most consequential contributions a technology consultant makes to an architectural project – and one of the most frequently underestimated. In fact, only about 25% of construction projects come within 10% of their original budget.2

When architects build technology budgets on placeholder numbers or outdated benchmarks, the gap between what was estimated and what things actually cost tends to show up at the worst possible time: during a bid review or, worse, mid-construction.

Accurate building technology cost estimating requires current market knowledge, familiarity with the systems being designed, and an understanding of how installation complexity, phasing, and site conditions affect costs. A consultant who brings these inputs to the SD phase gives the owner a defensible budget – and gives architects a number they can actually stand behind.

At TMC, we build our technology cost estimates from current pricing, real system designs, and 35+ years of experience across government, healthcare, education, airport, and enterprise projects. We don’t use placeholder numbers because our clients’ owners don’t have placeholder budgets.

4 Components Technology Specifications for Architects Should Include

The difference between a specification that protects your project and one that creates exposure often comes down to a few key components:

1. Scope Definition

A strong technology specification defines exactly what is and isn’t included in the contractor’s scope. Ambiguity about scope boundaries between trades – such as the interface between low-voltage technology systems and the electrical contractor – is a consistent source of disputes and change orders. Clear scope language eliminates the gray areas that become arguments.

2. System Performance and Design Standards

Specifications should define not just what is being installed, but what it needs to do and how it needs to be installed to do it. Performance standards, design criteria, and installation requirements give contractors clear targets – and give the architect and owner a basis for evaluating whether the installed work meets the intent.

Every ambiguity in a technology specification is a potential RFI.

3. Submittal and Testing Requirements

Failing to define submittal requirements or acceptance testing criteria can lead to contractors installing systems that meet the letter of the spec without meeting its intent. Define what should be submitted, what should be reviewed, and how systems should be tested at closeout upfront to protect the owner and support a clean handover.

4. Coordination Notes and Interface Requirements

Specs for AV, IT infrastructure, and other architectural project technology should include explicit coordination requirements – what the technology contractor is responsible for coordinating with other trades, what information they need from other contractors, and what they’re required to provide. This is the documentation that prevents “not my scope” disputes from holding up a project closeout.

 

MEP Coordination and Construction RFI FAQs

What Is MEP Coordination and Who Handles Technology?

MEP coordination is the process of reconciling mechanical, electrical, and plumbing systems so they fit together in the building without conflict. Technology systems share the same ceilings, pathways, and equipment rooms, so a technology consultant coordinates AV, IT, security, and low-voltage requirements alongside the MEP work to prevent clashes.

How Does MEP Coordination Prevent Change Orders?

Completing MEP coordination before construction documents are issued resolves conduit conflicts, equipment room sizing, and power and cooling gaps through redlines instead of field RFIs. When technology, MEP, and architectural requirements are reconciled during design, the gaps that would otherwise surface as change orders are caught on the drawings.

How Do You Avoid Technology Cost Overruns in Construction?

Avoiding technology cost overruns starts with accurate estimating during schematic design, built from current pricing and real system designs rather than placeholder benchmarks. Detailed, coordinated documents then compress scope ambiguity at the front end, which means fewer surprises during bidding and construction.

At What Project Phase Should an Architect Engage a Technology Consultant?

The highest-leverage time is at schematic design, where changes cost a fraction of what they cost at construction documents or in the field. A technology consultant for architects engaged at SD can translate owner requirements into infrastructure narratives and flag coordination issues before they are locked into the design.

How Do You Reduce RFIs on a Construction Project?

RFIs drop when construction documents are well coordinated and specifications are precise, because contractors have the information they need to build without asking. Completing MEP coordination before documents are issued, writing clear scope and performance requirements, and staying engaged through construction administration are the practices that most reliably reduce RFIs.

What Should Be in a Technology Scope for a Building Project?

A strong technology scope defines what is and is not included, sets system performance and design standards, specifies submittal and testing requirements, and includes coordination notes that define responsibilities at the boundaries between trades. Those four components remove the gray areas that become disputes and change orders.

How Does a Technology Consultant Reduce Project Risk?

A technology consultant reduces risk by catching coordination and documentation gaps during design and by maintaining continuity through construction. Because the same team that produced the documents responds to RFIs and evaluates owner changes against the existing design, decisions are faster and more consistent, which keeps the project moving.

Why Is Accuracy Important in Building Technology Cost Estimating?

Accurate estimating matters because only about a quarter of construction projects come within ten percent of their original budget, and technology is a frequent source of the gap. Estimates built from current market pricing and real system designs give owners a defensible budget and give architects a number they can stand behind.

 

Finish Technology-Intensive Projects With Fewer Surprises

The problems that generate RFIs, change orders, and budget overruns on technology-intensive projects aren’t inevitable. They’re almost always traceable to gaps in planning, coordination, and documentation that a qualified technology consultant addresses as a matter of course.

At TMC, we’ve been supporting architects on technology-intensive building projects since 1987 – across Divisions 25, 27, and 28, through schematic design, design development, construction documents, bidding, and construction administration. We produce coordinated drawings, accurate cost estimates, and specs that hold up under contractor and owner scrutiny – and we stay engaged through the end of the project to make sure what was designed is what gets built.

If you’re working on a project where technology complexity is a concern, contact our team to discuss how we can support your process – from early design through construction closeout.

Sources:

  1. https://www.digitalconstructionweek.com/why-construction-projects-still-struggle-with-failure-costs
  2. https://buildagent.to/blog/why-construction-projects-go-over-budget

Expert Insights

Read our blog for strategic guidance and analysis from TMC’s technology consultants.

How Does MEP Coordination Prevent Technology Cost Overruns in Construction?

TL;DR Technology cost overruns in construction almost always trace back to coordination gaps from the design phase – ...

What Questions Should I Ask an Architectural Technology Consultant?

When evaluating an architectural technology consultant for a building project, the questions you ask can help you ...

How To Evaluate an Architectural Technology Consultant for Your Building Project

TL;DR An architectural technology consultant should be engaged as a design-side professional – vendor-neutral, ...